INSTALLATION INSTRUCTIONS
|
1) Parts included in the enclosed list should be in the
transport pack.
2) TRAXLETM [1] should be oriented in north-south
direction (tolerance +5o). There have to be no shadows
(trees, other tracks etc.) on the installation area since 6 a.m. till 6
p.m.
3) TRAXLETM [1] should be mounted to the stand
[3].
Note: a) The stand [3] is not part of standard delivery. b) Different
types of stands can be used (e.g. pole stand).
4) Slope of the TRAXLETM [1] should be preferably adjusted
to local latitude. (Slope of the horizontal tracker should be 2-5°).
5) Rack [4] should be mounted on the TRAXLETM [1].
The pinhead A on the top rack profile have to fit into to
the hole A drilled in the TRAXLETM [1].
Transverse "L" profiles [7] should be fixed to the rack [4]. (TRAXLETM
longer than 3,5m)
6) Collectors [6] should be mounted on the rack [4]. Solar collectors
have to be very well balanced (see details in the User Manual and
Fig. "BALANCE"). Solar collectors have to be very well balanced also
during assembly. One panel is the only acceptable diffrence between
both sides of the rack during assembly.
7) Auxiliary solar panel [2] should be fixed to the TRAXLETM
[1]. The pinhead B on the auxiliary solar panel [2]
have to fit into to the hole B drilled in the TRAXLETM
[1]. Connector have to be plug in. It is strictly prohibited to attach
any instruments to the connector.
8) Output cable [8] have to be fixed to the TRAXLETM
not to the rack. Flexible loop have to be on the output axle.
9) The photo/video (not infrared) 300W halogen lamp have to be used
to move the complete system to East and West limits. The distance between
the lamp and the auxiliary solar panel [2] have to be at least 300mm
(to avoid heating). The tracking angle have to be more than 90°. |
DESCRIPTION OF EQUIPMENT - The mechanism is composed of one driving
unit TraXle [1], which is equipped with the primary solar collector [2]
with the twin function of powering the D.C. motor and following the motion
of the sun. The primary collector powers the motor, which is located in
the driving unit. Both sides of the axle are sealed to prevent the incursion
of dust or dampness. This guaranties overall long life and maintenance
free operation in the worst of the conditions. The solar panels are placed
in a rack [4], which is in turn mounted to the drive axle by U-bolts [5].
OPERATION AND MAINTENANCE - Thanks to the unique construction of the
unit it is unnecessary for any complex maintenance during regular operation.
Because of the turning nature of the equipment routine cleaning of the
solar panels is unnecessary as is the case with stationary panels. Only
in very few harsh climates will any more maintenance or cleaning be necessary
for the panels or the operating system. It is although advised to periodically
check the U-bolts holding the rack [4] and the anchoring points to make
sure they are not loose. Especially fasteners holding the output
axle have to be very well tightened.
BACKLASH - The TRAXLE is usually oscillating within backlash range
+
10° at windy conditions (no load backlash + 2° BOL). It is standard
operation mode of the tracker. The backlash together with innovative self-locking
transmission enables the tracker to work even at very strong winds where
other trackers does not work at all. Afternoon the oscillating rack is
touching the stand protected by plastic stopper. Later the rack is locked
to the stand (night oscillations are substantially limited).
FAILURES OF THE FUNCTION - If the equipment will stop functioning it
is possible there is a mechanical block or an imbalance. Then is important
to check the connection or angle of the directional panel with the driving
unit and repair the fault. If there is any damage to the driving panel
it must be replaced as per the instruction by the supplier. In case of
defect in the primary shaft consult the manufacturer. In any case
do not try to solve the defect or fault of the primary shaft by yourselves.
MATERIALS OF TraXle:
| TraXle (1) |
Sea water resistant Alu. alloy |
| Output shaft |
Standard Stainless steel (AISI 304) |
| Rack (4) |
Sea water resistant Alu. alloy |
| Fasteners |
Standard AISI 304 |
SAFETY IN MIND - It is necessary to fence the Tracker area to
keep out unwelcome persons such as children or animals in order to keep
them from harm. The fence will also reduce the effect of wind buffeting.
The anchoring must be able to withstand the most severe local wind conditions.
More than 0.1m3 of concrete per square meter of the PV
array area have to be used. Safety coefficient >2!
All installations must be done with the approval of local municipal
bylaws!
All responsibility for damage or injury to persons or property
resulting from not adhering to local bylaws is the responsibility of the
purchaser/ installer.
It is suggested to place well seen warning signs stating the
nature of the equipment.
BALANCE - The unit must be well balanced in order to work properly.
An
improper balance will result in a decrease in performance and reliability
(WARRANTY). On the vertical axis X the centre of gravity of the
rack has to be on the axis of the Traxle or slightly 1-5 mm
below the axis. The thickness of the distance washers is dependent on the
type of panel. Fig.1 shows how distance washers influence the balance of
the complete system. Distance washers are included in all TraXle sets and
it
have to be always used as indicated in the installation instructions.
At the same time, the panels must be equidistant from the Y to maintain
neutral balance. Hence, the panels must be of the same type and weight
on both sides of the TraXle. It is prohibited to attach instruments
to the rack which could cause imbalance of the system. Pre drilled
holes on the rack may be requested by ordering to accommodate the collectors
being used.
Fig.1 Influence of distance washers on balance of tilted
PV array.
MECHANICAL WARRANTY ON EQUIPMENT
Poulek Solar’s liability is limited to defects, which appear within
a period of one (1) year from the commissioning. Poulek Solar shall remedy
any defect in the equipment resulting from faulty materials and/or
workmanship, when such equipment is installed and used under normal conditions.
Any labour charges for troubleshooting, removal or replacement of the equipment
are not covered by this warranty. The part in question must be returned,
freight prepaid and accompanied by a copy of the original invoice,
to the Poulek Solar Co. Ltd. within the warranty period. The component
must be in its originally form without alterations or modifications which
will render the warranty null and void. Poulek Solar has no responsibility
for defects in the equipment to the extent caused by:
* Damage due to improper installation (especially imbalance)
* Misuse, abuse or improper storage or maintenance.
* Product impaired by severe conditions, such as excessive wind, ice,
storms, or other natural occurrences.
* Trackers with more than the intended number and type of modules mounted
on it.
* Damage due to improper packaging on return shipment.
* Damage due to chemical influence.
Type of Apparatus
TRAXLETM PST - 3/3 - SAL304
Technical specification
| Weight of the tracker |
Max. 8 kg/m2 |
| Standard size |
1-15m2 (0.1-2 kW) |
| Length of the TRAXLETM |
2-7 m |
| Weight of collectors |
Max. 20 kg/m2 |
| Tracking accuracy |
+10° (AM 1.5) |
| No load backlash (BOL) |
+2o |
| Tracking angle |
Max.120o |
| Max. static torque |
500-1.500 N.m |
| Area related torque |
2 N.m/m2 (AM 1.5) |
| Max. windspeed |
140 km/h |
| Backtracking time |
7 min. |
| Temperature range |
-30+80oC |
| Water & dust protection |
IP67 |
Poulek Solar, Ltd.
Velvarska 9, CZ-160 00 Prague,
Tel: +420 342 719, Fax: +420 224 312 981
info@solar-trackers.com
LIST OF ENCLOSED PARTS
The transport pack of the basic system accomodating N
pcs of PV modules should contain:
1 pc TRAXLE [1], 100mm dia.
1 pc Reference module [2]
N/2+1 pcs rack [4] "U" aluminum profiles
N/2+1 pcs M6 U-bolts [5] -100mm dia.
(to fix the rack to the TRAXLE)
4N pcs distance tubes 12mm dia. The tube is inserted
between the rack and the PV panel (see instal. instructions)
4N pcs of M6x40 (DIN 933) screws, nuts and washers (just
to screw together the rack and the PV panels)
2 pcs transverse "L" aluminum profiles [7] (which
will accomodatr PV modules-see instal. instructions). Only by TRAXLE longer
than 3,5m.
N+2 pcs of M6x16 (DIN 933) screws, nuts and washers (just
to screw together the rack and the transverse "L" al. profiles). Only by
TRAXLE longer than 3,5m.
There are additional parts included in the complete system:
2 pcs M6 U-bolts-23mm dia. (to fix the 70mm dia.
output tube to "legs")
4 pcs M6 flange nuts (DIN 6923) and washers (to fix the
output tube to "legs")
3 pcs Anchors (to fix the tripod to concrete foundations)
2 pcs Supporting (stand) legs [3] "U" aluminum profiles
(The output axle of the TRAXLE is fixed to the stand)
3 pcs Anchoring “U“ profiles with M8 screws, washers
and nuts (interface between tripod and anchors) |
|